What’s new?
Fall 2009 - Winter 2009 Steel Erection
Structural steel operations have begun. The first area of steel erection will occur at the Everett Street side of site. The steel will then be erected in a southerly direction towards Pound Hall. Steel erection is expected to be completed early 2010. The next phase of construction will be installation of the facade and interior mechanical systems. Part of the facade, the prominent arch entryway, has already been installed.