What’s new?
Removal of Wyeth Hall demolition debris continues with the remaining sections of the lower two floors and foundation scheduled for demolition and removal over the next two weeks. Pedestrian protection along Massachusetts Ave. and Everett Street is nearing completion adjacent to the Everett Street Garage. The Everett Street Garage is being prepared for demolition by the installation of protective wrap, sheathing and staging. Utility and loading lock relocation enabling work continues around the project.
|
 |