Woodhouse Preparation
Woodhouse Moves
Post-House Moves
Wyeth Hall
Demolition
Everett St. Garage Preparation for Demolition
Story Hall Conversion
Utility Work
Demolition of Everett St. Garage
Preparation for Slurry Wall
Slurry Wall Construction
|
 |
What’s new?
The Everett Street Garage is being prepared for demolition by the installation of protective wrap, sheathing and staging. Pedestrian protection along Massachusetts Ave. and Everett Street, adjacent to the Everett Street Garage, is complete. Utility and loading lock relocation enabling work continues around the project. |
 |